1st installment: steel frame work completed and rust proofing completed ————————pay 30%

2nd installment of the main roofing work completed (excluding roof terrace)

Interior floor paneling, interior walls completed. and the electric wires are completed ————————- Pay 20%

3rd installment: exterior wall paneling – exterior ceiling paneling completed——————————Pay 20%

4th installment: bathroom tile work – sanitary ware installation All internal ceilings-

All doors and windows – roof terrace completed.

Exterior and interior paint work 90% completed —————————————— Pay 20%

Part 5. The fourth job is 100% complete. Clean and remove all scraps.

Completed, connect the water pipes, treatment system, connect the electrical mains and test the electrical system

Tested the bathroom and equipment and completed —————————–Pay 10%

**In case of large work, high work value, can be paid in more than 5 installments

*** In the case of hiring a contractor only for wages : The contractor may request an advance payment of 2,000-3,000 baht for fuel.

to bring tools to work with us

Example of contractor pay

In the case of contractor wages, 3,000 baht per sq m., the house has a size of 3x5 m. = 15 sq.m. 3,000 x 15 = 45,000 baht.

In the case of hiring a contractor only for wages

1st installment: steel frame work completed and rust proofing completed———-pay 30% (13,500g)

2nd installment of the main roofing work completed (excluding roof terrace)

Interior floor paneling, interior walls completed. And the electric wires are completed ————- Pay 20% (9,000g)

3rd installment: exterior wall paneling – exterior ceiling paneling completed —————-Pay 20% (9,0008)

Installment 4. Bathroom tile work Install sanitary ware – all internal ceilings –

All doors and windows – roof terrace completed.

Exterior and interior paint work 90% completed —————————————— Pay 20% (9,0008)

Part 5. Paint work is 100% complete, clean and remove all scraps.

Completed, connect the water pipes, treatment system, connect the electrical mains and test the electrical system

Testing the bathroom and equipment and done ——————————————Pay 10 % (4,500g)

  1. Construction of the construction period Fiber cement steel frame house, no more than 36 sq m.

In the case of building a  house or a moving knock-down house

1st installment: sign a contract, receive a deposit, complete 30%

The 2nd installment of the steel frame work is completed and rust proofing is completed ———————— Collect 40%

3rd installment: ceiling, floor, wall, roof work

 Bathroom tile work (except grout work), sanitary ware, electrical system

 All doors and windows Paint work is 90% complete.

 ready to transport —————————————————- ———Keep 20%

     (*** 3rd installment, collect money before shipping to customers or when the car arrives at the land, collect money before installation)

4th installment of the house, collecting paint work, 100 % complete

 Connect water pipes, treatment systems, connect electrical mains and test the electrical system.

 Test the bathroom and equipment.

 Clean and collect all scraps and finish ——————Collect 10%

**In case of large work, high work value, should be divided into more than 4 installments.

*** Viewing the area in front of the event is important. to the difficulty of transportation It is a preliminary assessment that

Can the house be transported in, or do I have to build it on site?

Example of collecting installments for building a knock-down house, moving type

In case of selling a house, 13,000 baht per sq m. The house has a size of 3x5 m. = 15 sq.m. 13,000 x 15 = 195,000 baht.

In the case of building a moving knock-down house

1st installment: contract and complete—————————————— ———————- Save 30% (58,500฿)

The 2nd installment of the steel frame work is completed and rust proofing is completed ——————————- Collect 40% ( 78,000฿)

3rd installment: ceiling, floor, wall, roof work

 Bathroom tile work (except grout work), sanitary ware, electrical system

 All doors and windows Paint work is 90% complete.

 Ready to transport and install———————————————- ——————— Collect 20% (39,000฿)

  (*** 3rd installment, collect money before shipping to customers or when the car arrives at the land, collect money before installation)

4th installment of the house, collecting paint work, 100 % complete

 Connect water pipes, treatment systems, connect electrical mains and test electrical systems

 Test the bathroom and equipment

 Cleaning and collecting all scrap materials and finished ————————- Collect 10% (19,500฿)

**In case of large work, high work value, should be divided into more than 4 installments.

  1. Construction of the construction period Fiber cement steel frame house, no more than 36 sq m.

In the case of building a knock-down house on the customer’s land

1st installment: contract and complete—————————————— —————————-Keep 30%

2nd installment: steel frame work completed and rust proofing is completed ———————————– -Keep 30%

3rd installment: the main roofing work is completed (excluding the balcony roof)

Interior floor paneling, interior walls completed. and the electric wires are completed

Exterior wall paneling – exterior ceiling paneling completed—————————————- ———————Keep 20%

4th installment of the balcony roof work completed bathroom tile work

Install sanitary ware – all interior ceilings

All doors and windows are finished———————————————- ——————————- Collect 15%

5th installment of the paint job completed Clean and remove all debris.

Completed, connect the water pipes, treatment system, connect the electrical mains and test the electrical system

Test the bathroom and equipment and completed———————————————— ————Keep 5%

**In case of large work, high work value, can be Collecting more than 5 periods

Example of collecting installments for building a knock-down house on the customer’s land

In the case of building a house, 13,000 baht per sq m. The house has a size of 3x5 m. = 15 sq.m. 13,000 x 15 = 195,000 baht.

In the case of building a knock-down house on the customer’s land

1st installment: contract and complete—————————————— ———————- Save 30% (58,500฿)

2nd installment: steel frame work completed and rust proofing completed ——————————- 30% collected ( 58,500฿)

3rd installment: the main roofing work is completed, excluding the roof terrace)

Interior floor paneling, interior walls completed. and the electric wires are completed

Exterior wall paneling – exterior ceiling paneling completed—————————————- ——Save 20% (39,000฿)

4th installment of the balcony roof work completed bathroom tile work

install sanitary ware all internal ceilings

All doors and windows are finished———————————————- —————– Save 15% (29,250฿)

5th installment of the paint job completed Clean and remove all debris.

After completion, connect the water pipes, treatment system, and connect the electrical mains.

and test the electrical system Test the bathroom and equipment Completed —————————- Collect 5% (9,750฿)

**In case of large work, high work value, can be divided into more than 5 installments